Bordeaux (33) – tram

Expertise on Citadis 302 and 402 trains

Start date: 2020
End date: 2021

Details:

SAFRA, on behalf of Keolis Bordeaux, participated in the complete replacement of floors and floor mats on two types of trains, 302 and 402. These removals allowed Bordeaux Metropole to carry out structural surveys and analyses.

Figure 1. Corrosion report after removal of wooden floors

Figure 2 . Corrosion treatment of aluminium floor   

Bordeaux (33) – tram

Citadis 302/402 diagram change (2019-2020)

Start: 2019
End date: 2020

Details:
Bordeaux Metropole has entrusted SAFRA with the refurbishment of 74 CITADIS trains. This contract consists in the interior fitting out in order to offer to the users a better comfort.

The first prototype train will be realized from 15/04 to 18/04/2019
The second prototype trainset processed from 23/04 to 25/04/2019

Mr. Duprat, vice-president of Bordeaux Metropole in charge of transport, validated on 25/04/2019 the modifications and the new design. These modifications are subject to validation by the STRMTG (Service Technique des Remontées Mécanique et Transports Guidés).

Serial contract processed from 22/07/2019 to 31/12/2020. On average one train set per week.

 

Intérieur du tramway de Bordeaux rénové par SAFRA Rénovation After
Intérieur du tramway de Bordeaux avant le début des travaux de rénovation de SAFRA Before
Intérieur du tramway de Bordeaux rénové par SAFRA Rénovation After
Intérieur du tramway de Bordeaux avant les travaux de rénovation de SAFRA Before